[A] Once the production order is planned we can not change the targeted quantity of production order


[B] But if we have produced more quantity than the targeted quantity then we can add this extra quantity to the production order.


[C] Procedure to add this quantity is the same as adding finished goods. as you can see below we have completed all the production as targeted.



[D] Now we have produced 10 extra quantity, to add this to the em you will have to click on actions >> action >> finished Good as shown below.



[E] Now add the extra quantity in the quantity added column and click on the Save button.




[F]
 Now do the FG testing and your extra material will also get added in inventory.


Keywords: How to  extra quantity in PID, extra items were produced how to entry it