[A] To link a child BOM to Parent BOM, first open the parent BOM.

[B] Go to Actions(1) and click Edit(2).

[C] In the Raw Materials section, go to the raw material whose BOM you wish to select. Click the tree symbol next to it.

[D] Select the BOM number you wish to choose for the raw material. You can also create a new BOM if you want. Then click Save.

[E] The child and parent BOM have been linked. The raw material for which the child BOM was created has its constituent raw materials displayed in the parent BOM.